Project Digester in m³ Fermenter in m³ Fermenting rimains silo in m³ BHPP in kW Competencies
BGA Würdemann 325 370 2.000 240 1-8
BGA Kuhls 2 x 325 1.600 3.700 526 1-3
BGA Voltermann 1.349 2.015 2.814 526 1-8
BGA Erchinger 325 370 2.000 240 1-8
BGA Jacob 1.527 2.493 ~ 240 2-4
BGA Kruse 1.970 1.970 ~ 370 1-8
BGA Meyer 1.349 2.398 ~ 370 1-8
BGA Grube 1.970 1.970 ~ 370 1-2
BGA Heidmann 1.665 1.665 ~ 526 1-8
BGA Müller 325 370 2.000 240 1-8

 

    Legend:

    1. Technical conception
    2. Profitability analysis
    3. Contracting
    4. Financing
    5. Planning
    6. Construction
    7. Implementation
    8. Facility management

    BHPP...Block heat and power plant